Maintenance schedule & procedures
Maintenance schedule: Monthly — inspect all power posts for tightness, cleanliness, and oxidation, and confirm correct torque. Quarterly — record state of charge and resting voltage after a minimum 12-hour rest, and inspect/clean the STARTER ONLY post and Starter System terminals. Every 6 months — if in storage, confirm approximately 50% state of charge and recharge if required. Annually — run a full functional test: start-up sequence, load test, engine-start test, and CAN comms check.
Power terminal maintenance: de-energize and isolate the unit before touching any terminal. Inspect each post for oxidation, discolouration, or looseness. Clean lightly oxidised terminals and re-torque to the value in the Torque Specifications article.
Battery maintenance: keep storage humidity below 85% RH. For storage over 3 months, maintain approximately 50% state of charge and check every 6 months. For disposal, return the unit to a qualified recycler — never place it in general waste.
Starter System safe discharge procedure: 1) Switch the Starter System OFF by holding its button for 5 seconds. 2) Isolate and disconnect the relevant cables. 3) Connect a 12V resistive load (e.g. a 12V headlight) across the starter and ground points until the light goes out. 4) Verify the voltage across the starter post and ground is 2V or less before handling.
Routine Starter System care: periodically check the post and terminals for oxidation or looseness; clean and re-tighten as needed. No other field maintenance is required.
Storage: set the Shipping Switch to disabled. Store at approximately 50% state of charge, below 85% RH, away from direct heat sources. Attach a 12V trickle charger to the 12V post and ground post. Re-check charge every 6 months.